Question 1326 Deck General
70% to passThe last 1.0 meter (3.3 feet) of vapor piping before the vessel vapor connection must be painted _______________.
A
yellow/red/yellow
B
hi-visibility yellow
C
international orange
D
red/yellow/red
AI Explanation
The correct answer is D) red/yellow/red. The last 1.0 meter (3.3 feet) of vapor piping before the vessel vapor connection must be painted in the international color scheme of red/yellow/red. This color scheme is specified in the regulations to provide a clear visual indication of the hazardous nature of the vapor piping. The other answer choices, while potentially used for other purposes, do not meet the specific regulatory requirement for the color scheme of this critical section of the vapor piping.
Related Questions
Q@q.QuestionNumber:A
Q@q.QuestionNumber:Your vessel is off a lee shore in heavy weather and laboring. Which action shoul...
Q@q.QuestionNumber:The COASTAL DRILLER is in ocean transit in which the winds are not expected to e...
Q@q.QuestionNumber:Given the same water depth and mooring tension, the holding power of a 90 pound/...
Q@q.QuestionNumber:Which factor has the GREATEST influence on the squat of a vessel in shallow wate...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience with progress tracking.
Get the App