Question 2217 Deck General
70% to passBoth an approved B-V semi-portable fire extinguishing system and a fixed fire extinguishing system are required to protect the engine room on uninspected towing vessels whose construction was contracted for on or after what date?
A
February 1, 2002
B
August 27, 2003
C
April 29, 2004
D
April 29, 2005
AI Explanation
The correct answer is B) August 27, 2003. According to the Code of Federal Regulations (46 CFR 27.211), both an approved B-V semi-portable fire extinguishing system and a fixed fire extinguishing system are required to protect the engine room on uninspected towing vessels whose construction was contracted for on or after August 27, 2003. The other answer choices are incorrect because: A) February 1, 2002 is too early - the regulation came into effect after this date. C) April 29, 2004 and D) April 29, 2005 are both too late - the regulation was already in effect by those dates.
Related Questions
Q4818:A semisubmersible, while floating level, displaces 20,000 long tons. LCB is 3.0 ...
Q2498:A "loose" tow may cause all of the following EXCEPT _______________.
Q859:Which of the following are considered to be "road vehicles" that can be carried ...
Q4636:The DEEP DRILLER departs a fresh water port at a draft of 20 feet. What will be ...
Q3615:The design specifications for cranes and crane foundations on MODU's are set an...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app