Question 3672 Deck General
70% to passAfter cranes have been installed on offshore drilling units the hooks, hook block, slings, rib and other rigging must be load tested. This test must be performed once each _______________.
A
12 months
B
24 months
C
36 months
D
48 months
AI Explanation
The correct answer is D) 48 months. The reason for this is that according to the regulations set by the U.S. Coast Guard, offshore drilling units must have their cranes, hooks, hook blocks, slings, and other rigging equipment load tested once every 48 months (4 years). This requirement is in place to ensure the safe operation and continued functionality of this critical equipment over time. The other answer choices, such as 12 months, 24 months, and 36 months, are incorrect because they do not align with the Coast Guard's regulatory requirements for the frequency of these load tests on offshore drilling units.
Related Questions
Q@q.QuestionNumber:On tank vessels, fully charged fire extinguishers are considered semi-portable w...
Q@q.QuestionNumber:What term is not considered a "discharge" as it applies to the U.S. pollution re...
Q@q.QuestionNumber:As you hold a piece of manila line vertically in front of you, the strands run f...
Q@q.QuestionNumber:What is NOT a precaution to be taken when topping off?
Q@q.QuestionNumber:The holding power of an anchor is the _______________.
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience with progress tracking.
Get the App