70% to passEach emergency generator on a mobile offshore drilling unit, when tested, must be run under a full load for at least _______________.
A
one hour
B
two hours
C
ten hours
D
four hours
AI Explanation
The correct answer is B) two hours. According to the regulations for mobile offshore drilling units, each emergency generator on the unit must be run under a full load for at least two hours when tested. This ensures that the emergency generator can provide reliable backup power for an extended period in the event of a main power failure. The other answer choices are incorrect because one hour (A) is not long enough to fully test the generator's capabilities, while four hours (D) and ten hours (C) exceed the minimum requirement specified in the regulations.
Related Questions
Q3130:According to Pollution Prevention Regulations (33CFR), who is to sign the Oil Re...
Q952:When loading a tanker, you should _______________.
Q4023:You are planning to anchor in an area where several anchors have been lost due ...
Q2221:What does the term "end-for-end" refer to in regard to a wire towing hawser? ...
Q4451:The COASTAL DRILLER is elevated in 250 feet of water, experiencing 2 knots curre...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app