Question 4478 Deck General
70% to passThe DEEP DRILLER is on location during a storm. Windward anchor tensions begin to exceed the test tensions. To reduce tensions while minimizing offset over the well, you should _______________.
A
increase tension on the leeward chain
B
pay out more chain on the windward side
C
reduce tension on the leeward chains
D
connect an emergency tow wire to the work boat
AI Explanation
The correct answer is C) reduce tension on the leeward chains. Explanation: When anchor tensions on the windward side exceed the test tensions during a storm, the appropriate action is to reduce the tension on the leeward chains. This helps to minimize the offset over the well while also reducing the overall anchor tensions. Increasing tension on the leeward chain (option A) or paying out more chain on the windward side (option B) would not effectively reduce the overall anchor tensions. Connecting an emergency tow wire to the work boat (option D) is not the appropriate action to take in this situation.
Related Questions
Q4118:When piloting a vessel, how are visual references used to establish a constant r...
Q4599:While the DEEP DRILLER is operating as shown in Sample Form #4 (Drilling), casin...
Q3327:Smoking in bed on a MODU is prohibited _______________.
Q2253:Either one approved B-V semi-portable fire-extinguishing system or a fixed fire-...
Q2998:For towing vessels over 100 gross tons that are permitted to maintain a two-watc...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app