Question 4906 Deck General
70% to passThe COASTAL DRILLER is loaded as shown in the Sample Load Form Number 1 (Rig Move). If the drill water in drill water tanks 6 and 25 are discharged, what is the new draft?
A
8.26 feet
B
10.66 feet
C
10.88 feet
D
11.10 feet
AI Explanation
The correct answer is B) 10.66 feet. When the drill water in tanks 6 and 25 are discharged, the vessel's overall weight and displacement decrease, resulting in a reduction in draft. The Sample Load Form Number 1 (Rig Move) provides the necessary information to calculate the new draft after the discharge. The other options are incorrect because: A) 8.26 feet is too low, as the vessel's draft would not decrease that significantly. C) 10.88 feet and D) 11.10 feet are too high, as the draft would decrease after the discharge of the drill water.
Related Questions
Q@q.QuestionNumber:While a vessel is at sea, the mate on watch discovers a fire in one of the hatch...
Q@q.QuestionNumber:Which shape shown in illustration D016RR below would be displayed by a mobile of...
Q@q.QuestionNumber:What is the name of tackle number 1 as shown in illustration D029DG below?
Q@q.QuestionNumber:The type of carrier required to file a copy of freight tariffs would be the ___...
Q@q.QuestionNumber:The cheek length of a block in inches should be about _______________.
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience with progress tracking.
Get the App