Question 5094 Deck General
70% to passWhile drilling loaded as shown in Sample Load Form Number 4 (Drilling), the DEEP DRILLER suffers an unexpected but slowly increasing port and forward inclination. The wind and waves are light. This inclination could have been caused by _______________.
A
ballast tanks equalizing into tank 1P
B
the drilling crew dumping the mud
C
the failure of mooring lines 5 and 6
D
the drill string breaking
AI Explanation
The correct answer is A) ballast tanks equalizing into tank 1P. The slowly increasing port and forward inclination of the DEEP DRILLER while drilling loaded could have been caused by ballast tanks equalizing into tank 1P. This would affect the stability and trim of the vessel, leading to the observed inclination. The other options are incorrect because: B) dumping mud would not cause a slow, progressive inclination; C) failure of mooring lines 5 and 6 would likely cause a sudden, not gradual, change; and D) a broken drill string would not directly affect the vessel's stability and trim in this manner.
Related Questions
Q2211:How many B-II fire extinguishers must be in the machinery space of a 75-foot lon...
Q1076:The advantages of using an inert gas system on a tank vessel is that it provides...
Q3909:A stopper used in securing the ground tackle for sea that consists of a grab at...
Q3639:The required portable radio shall be stored in the proper location and be _____...
Q3784:According to regulations, a Master or person in charge of a MODU is required to ...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app