Question 520 Deck General
70% to passFor vessels fitted with cargo gear, an initial test of the units under a proof load shall be conducted. Subsequent tests and exams of the same nature shall be carried out at what time interval?
A
1 year
B
3 years
C
4 years
D
5 years
AI Explanation
The correct answer is D) 5 years. The reasoning behind this is that according to U.S. Coast Guard regulations, for vessels fitted with cargo gear, an initial test of the units under a proof load must be conducted, and subsequent tests and examinations of the same nature must be carried out at intervals not exceeding 5 years. This is to ensure the ongoing safety and reliability of the cargo gear. The other options are incorrect because they do not align with the 5-year interval requirement specified in the Coast Guard regulations for periodic testing of cargo gear on vessels.
Related Questions
Q3815:On a mobile offshore drilling unit it is required to _______________.
Q636:The signal man has both arms extended out, palms down, and is moving his arms ba...
Q2500:Which of the following responsibilities should you assume once you have agreed t...
Q3228:While in transit during heavy weather, the crew aboard a semisubmersible should ...
Q3229:A survival craft being used to pick up a person who has fallen overboard from a ...
Ready to test your knowledge?
Take a Deck General Practice Exam
Official Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app