Question 513Electricity & Electronics - Assistant Engineer
70% to passIn addition to high voltage circuit grounding with ground-connecting switching devices, for additional operator safety and confidence, portable grounding straps may be used. What is the proper procedure for connecting these portable grounding straps?
AThe common to hull ground connection and the phase connections to common can be made in any sequence.
BThe common to hull ground connection and the phase connections to common should all be made simultaneously.
CConnect the common connection to hull ground first, then connect the phase connections to common.
DConnect the phase connections to common first, then connect the common connection to hull ground.
AI Explanation
The correct answer is C) Connect the common connection to hull ground first, then connect the phase connections to common. This is the correct procedure because it establishes the ground connection first before making any other connections. Connecting the common to hull ground first ensures there is a proper ground path before the phase connections are made. This helps prevent potential shocks or other electrical hazards. The other options are incorrect because they do not follow the proper sequence of first establishing the ground connection.
Related Questions
Q281:Which of the following contactors or relays has a timing function for the transi...
Q515:Suppose it is desired to determine the integrity of the insulation of a 4160 VAC...
Q68:Diesel-generators #1 and #2 are operating in parallel at near full load capacity...
Q85:When a compound wound DC motor is cumulatively compounded, what does this mean? ...
Q483:Which of the methods listed is used to maintain equal load sharing between two c...
Ready to test your knowledge?
Take a Electricity & Electronics - Assistant Engineer Practice ExamOfficial Resources
Pass Your Coast Guard Licensing Exams!
Study offline, track your progress, and simulate real exams with the Coast Guard Exams app