Question 55Gas Turbine - Assistant Engineer
70% to passFor the GE LM2500 gas turbine engine shown in the illustration, the HP turbine 2nd stage nozzle vanes are cooled by which of the following? Illustration GT-0020

AFrame vent bleed air.
B13th stage compressor air.
C16th stage compressor air.
D9th stage compressor air.
AI Explanation
The correct answer is B) 13th stage compressor air. The HP turbine 2nd stage nozzle vanes in the GE LM2500 gas turbine engine are cooled by 13th stage compressor air. This is because the 13th stage of the compressor provides the highest pressure and temperature air within the engine, which is necessary to effectively cool the critical HP turbine nozzle vanes. The other answer choices are incorrect because frame vent bleed air (A) is not hot enough to provide adequate cooling, and the 16th stage (C) and 9th stage (D) compressor air does not have the required pressure and temperature characteristics to cool the HP turbine nozzle vanes.
Related Questions
Q26:How is the HP turbine rotor of the GE LM2500 gas turbine cooled? Q142:As shown in the illustration, what is the purpose of pressurizing the main beari... Q158:Aboard ship, single-shaft gas turbines are used mostly as prime movers for which... Q135:What type of starter is commonly used on smaller gas turbine engines? Q124:Which of the following is the principle that a magnetic speed sensor/pickup oper...
Ready to test your knowledge?
Take a Gas Turbine - Assistant Engineer Practice ExamOfficial Resources