Question 394General Subjects - 1st Asst/Chief
70% to passWhat project management scheduling chart is a bar chart with the activity or task descriptions displayed on the left and listed vertically from top to bottom, and the calendar displayed on the top and laid out horizontally from left to right?
APERT chart
BGantt chart
CPie chart
DCPM chart
AI Explanation
The correct answer is B) Gantt chart. A Gantt chart is a type of bar chart that is commonly used in project management to display the start and end dates of the various tasks or activities that make up a project. The activity or task descriptions are displayed on the left side of the chart and listed vertically from top to bottom, while the calendar is displayed on the top and laid out horizontally from left to right. The other answer choices are incorrect because: A) PERT chart is a network diagram that shows the interdependencies between tasks, C) Pie chart is a circular statistical graphic, and D) CPM chart is a project management tool that focuses on the critical path of a project.
Related Questions
Q242:One important objective of a practical skill demonstration for mariner certifica... Q195:Coast Guard regulations concerning marine sanitation devices may be found in ___... Q336:Fire and emergency training has three major components: knowledge sessions, skil... Q180:Which of the following statements is true concerning centrifugal pumps? Q148:When the oily-water separator, shown in the illustration, is in operation and pr...
Ready to test your knowledge?
Take a General Subjects - 1st Asst/Chief Practice ExamOfficial Resources