Question 197Motor Plants - 1st Asst/Chief
70% to passAs shown in the illustration, the function of component "1" is to_______________. Illustration MO-0128

Agenerate superheated steam to operate the turbo generator
Bevaporate circulating boiler water into saturated steam
Ccondense excess steam produced in the boiler
Dmaintain a water level in the steam drum
AI Explanation
The correct answer is B) evaporate circulating boiler water into saturated steam. The function of component "1" in the illustration MO-0128 is to evaporate the circulating boiler water into saturated steam. This is a critical component in the steam generation process, as it converts the liquid water into the steam that will then power the machinery onboard the vessel. The other answer choices are incorrect because: A) generating superheated steam is a different process that occurs downstream of the boiler; C) condensing excess steam is a separate function handled by other components; and D) maintaining the water level in the steam drum is a different task, not the primary function of component "1".
Related Questions
Q59:A pre-arrival test is being performed with the engine on bridge control. The ves... Q219:In accordance with Coast Guard Regulations (46 CFR Part 112), which of the liste... Q173:Why should the main steam stop valve of an auxiliary boiler be eased off its sea... Q106:A motor vessel has two centrifuges to pre-treat fuel to the engine(s) which may ... Q192:Waste heat boilers may be equipped with vents on the feedwater heater heads to _...
Ready to test your knowledge?
Take a Motor Plants - 1st Asst/Chief Practice ExamOfficial Resources