70% to passAccording to 46 CFR's, a fixed foam system aboard a tank vessel constructed in 1968, must be designed to supply foam for a minimum of _______________.
A3 minutes
B7 minutes
C12 minutes
D15 minutes
AI Explanation
The correct answer is A) 3 minutes. According to 46 CFR 32.20-20, a fixed foam system aboard a tank vessel constructed in 1968 must be designed to supply foam for a minimum of 3 minutes. This regulation specifies the minimum design requirements for fixed foam fire extinguishing systems on tank vessels to ensure adequate fire suppression capability. The other options are incorrect because they do not align with the 46 CFR regulation for tank vessels constructed in 1968. Options B, C, and D specify longer foam supply durations that are not required for this particular vessel.
Related Questions
Q283:The difference between the starboard and port drafts caused by a transverse shif... Q147:A new ocean going ship of 2000 gross tons having an inoperative oily water sepa... Q340:During repairs it is necessary to replace an existing vessel bulkhead. Drawings ... Q126:When fighting a liquefied natural gas fire, you should _______________. Q351:Where are "prohibited oil spaces" specified in the Pollution Prevention Regulati...
Ready to test your knowledge?
Take a Safety & Environmental - 1st Asst/Chief Practice ExamOfficial Resources