Question 289Steam Plants - Assistant Engineer
70% to passWhen preparing to hydrostatically test water-tube boilers, you should _______________.
Aremove all inspection plates and manhole covers as required by the marine inspector
Bfill the boiler with water not less than 70°F
C71.1°C)
Dmake arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure
AI Explanation
The correct answer is D) make arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure. When preparing to hydrostatically test water-tube boilers, the regulations require that the main and auxiliary steam stops be tested simultaneously with both water and steam pressure. This ensures that all the boiler components, including the main and auxiliary steam stops, are properly functioning under the increased pressure of the hydrostatic test. The other options are incorrect because they do not address the specific requirement for testing the steam stops under both water and steam pressure.
Related Questions
Q@q.QuestionNumber:The items labeled "D" and "M" as indicated on the illustration are commonly call... Q@q.QuestionNumber:In a boiler automation system, if a burner fuel oil solenoid valve continually t... Q@q.QuestionNumber:Which of the following items should be checked each time the firing rate or forc... Q@q.QuestionNumber:If the main condenser were operating at a vacuum of 28.5" Hg, a condensate disch... Q@q.QuestionNumber:In a cross-compounded turbine propulsion plant, steam enters the _______________...
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience.
Get the App