Question 289Steam Plants - Assistant Engineer
70% to passWhen preparing to hydrostatically test water-tube boilers, you should _______________.
Aremove all inspection plates and manhole covers as required by the marine inspector
Bfill the boiler with water not less than 70°F
C71.1°C)
Dmake arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure
AI Explanation
The correct answer is D) make arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure. When preparing to hydrostatically test water-tube boilers, the regulations require that the main and auxiliary steam stops be tested simultaneously with both water and steam pressure. This ensures that all the boiler components, including the main and auxiliary steam stops, are properly functioning under the increased pressure of the hydrostatic test. The other options are incorrect because they do not address the specific requirement for testing the steam stops under both water and steam pressure.
Related Questions
Q32:A boiler feed stop valve must be mounted _______________. Q234:According to the illustration, what part number identifies the "air door handle"... Q71:A secondary function of the refractory installed in a marine boiler is to ______... Q437:Improper water washing of the water-tube boiler firesides can cause ____________... Q439:According to the illustration of a typical boiler furnace rear wall, which item ...
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources