Question 588Steam Plants - Assistant Engineer
70% to passThe jacking gear must be engaged as quickly as possible when securing the main turbines in order to _______________.
Apermit rapid cooling of the reduction gears
Bmaintain a constant supply of lube oil to the main unit
Cprevent the stern tube bearing from overheating
Dprevent uneven cooling of the turbine rotors
AI Explanation
The correct answer is D) prevent uneven cooling of the turbine rotors. When securing the main turbines, the jacking gear must be engaged as quickly as possible to prevent uneven cooling of the turbine rotors. This is because rapid cooling can cause thermal distortion and stresses in the rotor, which can lead to damage. Engaging the jacking gear helps maintain an even, controlled cooling process to avoid these issues. The other options are incorrect because they do not directly address the need to prevent uneven cooling of the turbine rotors, which is the primary reason for engaging the jacking gear quickly when securing the main turbines.
Related Questions
Q383:The leakage of air into the pump casing by way of the packing gland of a condens... Q597:An energy loss associated with a reaction turbine, but not an impulse turbine, i... Q187:Which of the actions listed should be carried out immediately after securing the... Q444:A boiler accumulation test is used to measure the _______________. Q378:What is the cause of 'laning' in a boiler tube bank?
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources