Question 731Steam Plants - Assistant Engineer
70% to passHow is an excess of turbine gland seal steam remedied?
AIt is directed to the gland exhaust condenser.
BIt is recirculated via the loop seal.
CIt exhausts to atmosphere.
DIt drains to the makeup feed tank.
AI Explanation
The correct answer is A) It is directed to the gland exhaust condenser. Excess turbine gland seal steam is directed to the gland exhaust condenser to be condensed and returned to the feedwater system. This prevents the excess steam from escaping to the atmosphere, which would be wasteful and potentially hazardous. The other options are incorrect because recirculating the steam via a loop seal (B) is not the proper method for dealing with excess steam, exhausting it to the atmosphere (C) would be wasteful and polluting, and draining it to the makeup feed tank (D) would not be an effective way to handle the excess steam.
Related Questions
Q726:During maneuvering, a vessel has just reached full ahead from a dead slow condit... Q332:The variable capacity pressure atomizing fuel oil burner functions to __________... Q386:Testing boiler water for chloride content will indicate the amount of __________... Q447:On a boiler safety valve, the blow down adjusting ring is locked in place by a _... Q250:Steam tables can be used to obtain the _______________.
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources