Question 89Steam Plants - Assistant Engineer
70% to passWhen preparing to cut a boiler in on the line, you determine that the steam pressure of the incoming boiler is about 5 psig above line pressure. Which of the following steps should you take next?
AOpen the desuperheated steam stop.
BTest the hand relieving gear.
COpen the superheater vent.
DLight off additional burners.
AI Explanation
The correct answer is A) Open the desuperheated steam stop. When the incoming boiler steam pressure is slightly higher than the line pressure, the proper next step is to open the desuperheated steam stop. This allows the higher pressure steam to slowly equalize with the lower line pressure, preventing a sudden rush of steam that could damage equipment. The other options are incorrect, as they do not directly address the need to safely equalize the pressure difference before cutting the boiler in on the line.
Related Questions
Q107:An obstruction in the top connection of a boiler gage glass will cause the _____... Q537:In the diagrammatic arrangement of the thrust bearing, shown in the illustration... Q332:The variable capacity pressure atomizing fuel oil burner functions to __________... Q734:Which of the following systems can normally be supplied by auxiliary exhaust ste... Q684:Which of the following types of bearing lubrication schemes can carry the highes...
Ready to test your knowledge?
Take a Steam Plants - Assistant Engineer Practice ExamOfficial Resources