70% to passWhen water washing a boiler, the proper sequence for washing the sections should be the _______________.
Agenerating tubes, superheater, and then economizer
Bscreen tubes, generating tubes, and then superheater
Csuperheater, economizer, and then generating tubes
Deconomizer, superheater, generating, and then screen tubes
AI Explanation
The correct answer is D) economizer, superheater, generating, and then screen tubes. The proper sequence for washing the sections of a boiler is to start with the economizer, then move to the superheater, followed by the generating tubes, and finally the screen tubes. This sequence ensures that the water flow effectively cleans the boiler from the least to the most critical components. The other options are incorrect because they do not follow the proper order. For example, option A starts with the generating tubes instead of the economizer, while option B skips the economizer entirely. Option C reverses the order of the economizer and superheater.
Related Questions
Q213:Which area shown in the illustration will offer the most resistance to heat tran... Q167:One boiler of a two boiler plant has ruptured a tube and the water cannot be mai... Q401:Which of the listed operational checks should be made "continuously" on the main... Q339:The main propulsion turbine can be damaged by _______________. Q2:According to the illustration, what part number identifies the "igniter"? Illust...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources