70% to passIf the maximum steam generating capacity of a boiler is increased Coast Guard Regulations
AA
BB
CC
DD
AI Explanation
The correct answer is D. According to U.S. Coast Guard regulations, if the maximum steam generating capacity of a boiler is increased, the vessel must be re-inspected and the captain's license must be endorsed to reflect the increased capacity. This is because the increased steam generation capacity represents a significant change to the vessel's equipment and systems, which must be evaluated for safety and compliance purposes. The other answer choices are incorrect because they do not accurately reflect the Coast Guard's regulatory requirements in this scenario.
Related Questions
Q238:Excessive water loss from the main feed system can be caused by _______________. Q254:Scale in the air ejector first-stage nozzle could cause a decrease in the ______... Q361:The three wing device in the unit illustrated is maintained in its position by i... Q310:Which of the following is used to hold the poppet valves closed in a turbo-gener... Q240:Air accumulated in the inter condenser of the air ejector assembly is discharged...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources