Question 398Steam Plants - 1st Asst/Chief
70% to passThe over speed tripping device installed on an auxiliary turbine is automatically actuated by _______________.
Acentrifugal force
Bpneumatic force
Chigh back pressure
Dhydraulic pressure
AI Explanation
A) centrifugal force is the correct answer. The over speed tripping device installed on an auxiliary turbine is automatically actuated by centrifugal force. As the turbine's rotational speed increases beyond a safe limit, the resulting centrifugal force acts on a mechanism within the device, causing it to trip and shut down the turbine to prevent damage. The other options are incorrect because: B) Pneumatic force is not the primary mechanism for over speed tripping. C) High back pressure may be a consequence of over speed, but does not directly actuate the tripping device. D) Hydraulic pressure is not the main force that triggers the over speed tripping mechanism.
Related Questions
Q138:To assure a long service life for boiler refractory materials after installation... Q368:The jacking gear on main propulsion turbines can be used to _______________. Q359:While a vessel is underway the low-pressure turbine high-speed pinion is damaged... Q176:Which combustible element in fuel oil is considered a significant and major sour... Q50:Which of the following locations could desuperheated steam be considered to occu...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources