Question 41Steam Plants - 1st Asst/Chief
70% to passWhen preparing to hydrostatically test water-tube boilers, you should _______________.
Aremove all inspection plates and manhole covers as required by the marine inspector
Bmake arrangements for simultaneously testing main and auxiliary steam stops with water and steam pressure
Chave the boiler warmed to a temperature not exceeding 100°F
DD
AI Explanation
The correct answer is A) remove all inspection plates and manhole covers as required by the marine inspector. When preparing to hydrostatically test water-tube boilers, you should remove all inspection plates and manhole covers as required by the marine inspector. This allows the inspector to thoroughly inspect the interior of the boiler and ensure its integrity before the hydrostatic test is conducted. The other answer choices are incorrect because: B) is not necessary for the hydrostatic test itself, but may be required during other inspections. C) is not relevant, as the boiler should be at ambient temperature for the hydrostatic test.
Related Questions
Q@q.QuestionNumber:Excessive carbon dioxide formed by improper chemical treatment in the boiler may... Q@q.QuestionNumber:With vacuum up and the main propulsion turbine standing by while awaiting engine... Q@q.QuestionNumber:After starting the main lube oil pump in a gravity-type lube oil system, you sho... Q@q.QuestionNumber:Boilers equipped with steam atomizers can operate over a wide load range without... Q@q.QuestionNumber:Slag buildup on boiler furnace refractory is undesirable because it causes _____...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience.
Get the App