Question 158Steam Plants - QMED
70% to passThe jacking gear must be engaged as quickly as possible when securing the main turbines in order to _______________.
Aprevent uneven cooling of the turbine rotors
Bmaintain a constant supply of lube oil to the main unit
Cprevent the stern tube bearing from overheating
Dpermit rapid cooling of the reduction gears
AI Explanation
The correct answer is A) prevent uneven cooling of the turbine rotors. When securing the main turbines, the jacking gear must be engaged as quickly as possible to prevent uneven cooling of the turbine rotors. This is because rapid cooling of the turbine rotors can lead to thermal distortion and potential damage to the turbine components. Engaging the jacking gear ensures that the rotors cool evenly and prevents any undue stresses on the turbine. The other answer choices are incorrect because they do not directly address the primary purpose of engaging the jacking gear, which is to ensure even cooling of the turbine rotors.
Related Questions
Q127:The lube oil coolers installed in a gravity lubricating oil system are located b... Q176:During the routine inspection of an operating centrifugal lube oil purifier, you... Q30:Which of the following labeled items of the illustrated air register and burner ... Q95:In a single furnace boiler, where is the steam typically cooled for use as auxil... Q167:Cooling water to the vent condenser in a DC heater is supplied by the __________...
Ready to test your knowledge?
Take a Steam Plants - QMED Practice ExamOfficial Resources