You are the operator of a 296 GRT uninspected towing vessel. Its construction was contracted for after August 27, 2003. In addition to the hand portable fire extinguishers, how much other fire extinguishing equipment are you required to have on board?
AI Explanation
The correct answer is D) Both an approved B-V semi-portable fire extinguishing system and a fixed fire extinguishing system.
This is the correct answer because the regulations require an uninspected towing vessel of 296 GRT that was contracted for after August 27, 2003 to have both an approved B-V semi-portable fire extinguishing system and a fixed fire extinguishing system, in addition to the required hand portable fire extinguishers.
The other options are incorrect because option A only requires a water mist system and a CO2 system, option B only requires a B-V semi-portable system and a water mist system, and option C only requires either a B-V semi-portable system or a fixed system, whereas the regulations mandate both a B-V semi-portable system and a fixed system.
Related Questions
#2675 Which type of fixed fire protection system is approved for use on board uninspected vessels? #2676 You are the operator of a 295 GRT uninspected towing vessel. Which type of fire extinguishing system is required on your vessel, if its construction was contracted for before August 27, 2003? #2678 You are the operator of a 290 GRT uninspected towing vessel whose construction was contracted for after August 27, 2003. Which type of semi-portable fire extinguishing system is required on your vessel? #2679 Uninspected towing vessel fire protection regulations apply to which of the following vessels? #2680 Fire protection regulations apply to those towing vessels _______________.