Question 3430Deck General70% to pass
What should be done after repairing a surface crack on a link of anchor chain by grinding?
AI Explanation
The correct answer is C) Examine the area by magnetic particle inspection.
After repairing a surface crack on a link of anchor chain by grinding, it is crucial to inspect the area using magnetic particle inspection. This non-destructive testing method can detect any remaining cracks or flaws in the chain link that may have been missed during the grinding process. This is important to ensure the structural integrity of the chain and prevent potential failure during use. The other options, such as post-heat treatment (A) or galvanizing (B), are not sufficient to verify the quality of the repair. Replacing the entire chain (D) may not be necessary if the inspection confirms the integrity of the repaired link.
Related Questions
#3428 The requirements for obstruction lights on mobile offshore drilling units apply on all waters _______________.#3429 A mobile offshore drilling unit is on the waters of the U.S. Outer Continental Shelf. It has a length of 220 feet and a breadth of 190 feet. Where must the obstruction lights be located? #3431 While being towed at a 19.5 foot draft, the DEEP DRILLER experiences single amplitude rolls of 10° with a period of 8 seconds. You should _______________.#3432 Where will you find the requirements for the lights that must be displayed on a mobile offshore drilling unit that is being towed? #3433 For the purposes of the International Rules of the Road, a non-self-propelled mobile offshore drilling unit under tow is considered to be a _______________.