Certificates of Inspection for offshore drilling units are issued for a period of _______________.
AI Explanation
The correct answer is B) 24 months.
Certificates of Inspection (COIs) for offshore drilling units are issued for a period of 24 months, as per the regulations outlined in 46 CFR 107.211. This regulation states that COIs for mobile offshore drilling units must be renewed every 24 months.
The other answer choices are incorrect because 12 months (A) is too short, 36 months (C) and 48 months (D) are too long for the required COI renewal period for these types of offshore drilling units.
Related Questions
#3582 Each hose in the fuel transfer system for helicopter refueling must meet the standards of the _______________.#3583 Compliance with the terms of the load line certificate on a MODU is the responsibility of the _______________. #3585 Each buoyant work vest must be _______________.#3586 Who is responsible for insuring that the accommodations on a mobile offshore drilling unit are maintained in a clean and sanitary condition? #3587 For means of abandonment of a MODU, which type of embarkation does not require prior approval by the Coast Guard?