Question 4484Deck General70% to pass
The COASTAL DRILLER is loaded as shown in the Sample Load Form #1 (Rig Move). How much more variable load in kips can be placed on the unit if winds increase to greater than 70 knots?
AI Explanation
The correct answer is A) 0 kips.
When winds exceed 70 knots, the COASTAL DRILLER must be secured for heavy weather operations. This means no additional variable load can be placed on the unit, as it needs to be in a stable configuration to withstand the high winds. The load form shows the unit's configuration for rig move, which is the maximum allowable loading. Adding more weight when winds are greater than 70 knots could jeopardize the unit's stability and safety, so no additional variable load is permitted.
The other options are incorrect because they would allow for more weight to be added, which would be unsafe and against the regulations for heavy weather operations.
Related Questions
#4482 The COASTAL DRILLER is loaded as shown in the Sample Load Form #1 (Rig Move). What is the margin on the maximum allowable KG if winds increase to greater than 70 knots, and the TOC is changed to the recommended value? #4483 The COASTAL DRILLER is loaded as shown in the Sample Load Form #1 (Rig Move). How much more variable load in kips can be placed on the unit if winds remain less than 70 knots? #4485 The COASTAL DRILLER is loaded as shown in the Sample Load Form #1 (Rig Move). What is the margin on the maximum allowable KG if winds remain less than 70 knots? #4486 The COASTAL DRILLER is loaded as shown in the Sample Load Form #1 (Rig Move). While in field transit, the wind speeds are predicted to increase above 70 knots. What would be the new KGL if the legs are lowered to the recommended value? #4487 If a severe storm threatens the COASTAL DRILLER while elevated, the setback in the derrick should be lowered and placed in the pipe rack. Its weight should be accounted for as _______________.