Question 200Electricity/Electronics - 1st Asst/Chief70% to pass
Before any work on electrical or electronic equipment is performed, which of the following precautions should be carried out?
AI Explanation
The correct answer is C) Secure and tag the supply circuit breaker in the open position.
This is the correct answer because it is the proper safety precaution to take before working on any electrical or electronic equipment. Securing and tagging the supply circuit breaker in the open position ensures that the circuit is de-energized and prevents accidental re-energization, which could lead to serious injury or damage.
The other options are incorrect because A) stationing a man at the circuit supply switch does not physically disconnect the power, B) bypassing interlocks defeats important safety mechanisms, and D) de-energizing the applicable switchboard bus may not isolate the specific circuit where work is being performed.
Related Questions
#198 To test fuses in an energized circuit, what testing apparatus or meter should be used? #199 In order to definitively determine whether or not fuse "1", shown in the illustration is blown using an on-line testing technique, across what points would you connect the voltmeter leads? Illustration EL-0062 #201 In addition to short circuits and sustained overloads, in what other situation are fuses likely to blow? #202 When replacing a fuse with one of a ampere higher rating than the original, which of the following is true? #203 As shown in the illustration, which electrical symbol represents a PNP type bipolar junction transistor? Illustration EL-0065