Question 588Steam Plants - Assistant Engineer70% to pass
The jacking gear must be engaged as quickly as possible when securing the main turbines in order to _______________.
AI Explanation
The correct answer is D) prevent uneven cooling of the turbine rotors.
When securing the main turbines, the jacking gear must be engaged as quickly as possible to prevent uneven cooling of the turbine rotors. This is because rapid cooling can cause thermal distortion and stresses in the rotor, which can lead to damage. Engaging the jacking gear helps maintain an even, controlled cooling process to avoid these issues.
The other options are incorrect because they do not directly address the need to prevent uneven cooling of the turbine rotors, which is the primary reason for engaging the jacking gear quickly when securing the main turbines.
Related Questions
#586 To prevent damage to the turning gear mechanism, which of the following procedures must be carried out before the turning gear is engaged? #587 To stop the rotor of a main turbine while underway at sea you should _______________.#589 In securing the main turbines, steam to the second stage air ejectors should be left on for a short period of time in order to _______________.#590 The FIRST step in breaking vacuum on a main turbine unit should be to _______________.#591 A pressure drop occurs across both the moving and fixed blades of a reaction turbine as a result of the _______________.