Question 188Steam Plants - QMED70% to pass
When blowing tubes on an integral superheat boiler fitted with an economizer, the operating sequence to be followed is recommended by the manufacturer. What section of the boiler is generally blown first and last?
AI Explanation
The correct answer is B) Economizer section.
The economizer section of the boiler is generally blown first and last when blowing tubes on an integral superheat boiler fitted with an economizer. This is because the economizer, being the last heat exchanger in the boiler system, is most susceptible to fouling and requires more frequent cleaning to maintain efficient heat transfer. Blowing the economizer section first and last helps to dislodge any accumulated deposits and ensure optimal boiler performance.
The other options are incorrect because the superheater section, generating tube bank section, and screening tube section are not the primary focus of the tube blowing sequence, which is typically centered on the economizer.
Related Questions
#186 Serious tube leaks in the air ejector after condenser assembly may cause _______________.#187 When placing a cleaned and properly made up atomizer in the spare atomizer rack, how should the atomizer be stored? #189 When blowing tubes, what is the determining factor in deciding how many revolutions of rotation of a soot blower element are required? #190 When performing a bottom blow on a boiler, what valve is spun open quickly? #191 When cleaning boiler fuel oil atomizer parts, what type of cleaning tool should NEVER be used?