Question 297Steam Plants - 1st Asst/Chief
70% to passAfter starting the main lube oil pump in a gravity-type lube oil system, you should verify that the gravity tanks are full by _______________.
Asounding the gravity tanks
Bobserving the flow from the bearings
Csounding the lube oil sump
Dobserving the overflow sight glass
AI Explanation
The correct answer is D) observing the overflow sight glass. In a gravity-type lube oil system, the main lube oil pump draws oil from the gravity tanks. After starting the pump, the proper way to verify that the gravity tanks are full is to observe the overflow sight glass. This allows you to confirm that the tanks are at the proper level and that the oil is circulating through the system as intended. The other options are incorrect because sounding the tanks (A) or the sump (C) would not directly indicate whether the gravity tanks are full, and observing the flow from the bearings (B) would not provide a clear indication of the gravity tank level.
Related Questions
Q@q.QuestionNumber:If the salinity indicator periodically registers high salinity in the main hotwe... Q@q.QuestionNumber:The primary function of a flame safeguard system, as used on an automatically fi... Q@q.QuestionNumber:Coast Guard Regulations Q@q.QuestionNumber:Which of the listed refractory materials is composed of wool fibers and clay bin... Q@q.QuestionNumber:One factor for determining the minimum feed water inlet temperature to a boiler ...
Ready to test your knowledge?
Take a Steam Plants - 1st Asst/Chief Practice ExamOfficial Resources
Want to practice with timed exams?
Download Coast Guard Exams for the full exam experience.
Get the App