Question 4280Deck General70% to pass
Among the valves to open on the DEEP DRILLER, if you have to transfer ballast from Tank 1P to Tank 10S using #1 ballast pump, is valve _______________.
AI Explanation
The correct answer is A) 33 Starboard.
To transfer ballast from Tank 1P to Tank 10S using the #1 ballast pump, you would need to open valve 33 Starboard. This valve connects the #1 ballast pump to Tank 1P, allowing the pump to transfer the ballast from that tank. Valve 33 Port, 44 Port, and 44 Starboard would not be the correct valves to open for this operation.
The reasoning behind this is based on the layout and configuration of the ballast system on the DEEP DRILLER, which a US Coast Guard Captain's License exam candidate would need to be familiar with.
Related Questions
#4278 In storm conditions, with the wind and waves from the port bow of the DEEP DRILLER in 600 feet water depth, the offset is 9%. Completely slacking mooring lines 5 and 6 reduces the offset to _______________.#4279 When removing the cap from a sounding tube on a MODU, the sound of air escaping indicates the tank _______________.#4281 On the DEEP DRILLER, among the port-side valves to open when deballasting from ballast tank 2P is valve _______________.#4282 The COASTAL DRILLER, elevated in 200 feet of water with 2 knots current, 30 foot waves, and wind speeds of 60 knots may continue drilling if the maximum leg reaction is less than _______________.#4283 In the event the motion of the DEEP DRILLER is such that critical motion limits are exceeded, you should _______________.