Question 4344Deck General70% to pass
What port-side valves must be open to transfer ballast from Tank 10P to Tank 1P on the DEEP DRILLER, using the Port #1 ballast pump?
AI Explanation
The correct answer is B) 23, 35, 34, 33, 43, and 2.
To transfer ballast from Tank 10P to Tank 1P on the DEEP DRILLER using the Port #1 ballast pump, the following port-side valves must be open:
- Valve 23 (to allow water to flow from Tank 10P)
- Valves 35, 34, and 33 (to allow the water to flow through the piping system)
- Valve 43 (to allow the water to enter Tank 1P)
- Valve 2 (to allow the ballast pump to draw water from the system)
The other options are incorrect because they either do not include all the necessary valves (C and D) or include the wrong valve (A).
Related Questions
#4342 What port-side valves must be open to transfer ballast from Tank 1P to Tank 10P on the DEEP DRILLER using the Port #1 ballast pump? #4343 A semisubmersible is more likely to experience structural stresses during heavy weather when _______________.#4345 The COASTAL DRILLER, elevated in 100 feet of water with 0 knots current, 30 foot waves, and wind speeds of 50 knots may continue drilling if the maximum leg reaction is less than_______________. #4346 Among the valves on the DEEP DRILLER which may be opened when using the Salt-Water Service Pump to pump water into Tank 1P is _______________.#4347 The COASTAL DRILLER, while in an ocean transit, experiences a single amplitude roll of 8 degrees. What is the minimum period of motion which does not exceed the design limits of the legs?