Coast Guard Exams
Question 52Gas Turbine - Assistant Engineer70% to pass

For the GE LM2500 gas turbine shown in the illustration, the 9th stage bleed air is used for which of the following? Illustration GT-0017

Diagram for question 52
AI Explanation
The correct answer is C) Power turbine cooling. The 9th stage bleed air from the GE LM2500 gas turbine is used for power turbine cooling. The power turbine is responsible for extracting power from the high-pressure turbine exhaust to drive the compressor. Directing the high-pressure, high-temperature 9th stage bleed air to the power turbine helps cool the blades and other components, improving efficiency and preventing thermal damage. The other answer choices are incorrect because: A) is for the high-pressure turbine, not the power turbine; B) is for the compressor balance piston, not the power turbine; and D) is for sump pressurization and cooling, not the power turbine.