Question 415General Subjects - 1st Asst/Chief70% to pass
Which of the following statements represents acceptable practice for heavy fuel oil storage tank heating?
AI Explanation
The correct answer is B) The heavy fuel oil storage tanks currently on suction (or shall be within 24 hours) should be maintained 5-10°C above the fuel pour point until the fuel is transferred.
This is the correct answer because maintaining the heavy fuel oil storage tanks at a temperature 5-10°C above the fuel pour point ensures the fuel remains in a liquid state and can be easily transferred and used. The pour point is the temperature at which the fuel becomes too thick to flow, so keeping the tanks above this temperature prevents the fuel from solidifying or becoming too viscous to pump.
The other options are incorrect because: A) maintaining the tanks 5-10°C below the pour point would cause the fuel to solidify, making it difficult to transfer; C) maintaining the tanks 5-10°C below the flash point would be an unsafe practice, as the flash point is the temperature at which the fuel can ignite; and D) maintaining all tanks above the pour point for the entire voyage is unnecessary and would result in wasted energy.
Related Questions
#413 If two centrifuges are to be simultaneously used in series to treat residual fuel contaminated with both water and solids, how should the centrifuges be configured? #414 Which of the following statements represents acceptable practice for heavy fuel oil settling tank heating? #416 For the most efficient centrifuging of residual fuels on motor vessels, the lower the viscosity of the fuel as achieved by preheating, the more efficiently solids and moisture can be removed. For planning purposes, what is the typically the recommended upper limit of preheating for residual fuel oil centrifugation on motor ships? #417 In new construction or during significant steel plate replacements, what is the procedure of 'line heating'? #418 Vibration analysis can provide comparative data of operating condition of rotating machinery. At what positions should such readings be taken at bearing housings and foundations?