Question 585Steam Plants - Assistant Engineer70% to pass
When securing a main propulsion turbine equipped with carbon packing glands, the vacuum should always be broken before securing the gland seal steam because _______________.
AI Explanation
The correct answer is C) cold air rapidly entering the gland may result in damage to the carbon segments and sealing surfaces.
The reasoning behind this is that when securing a main propulsion turbine equipped with carbon packing glands, it's crucial to break the vacuum before securing the gland seal steam. This is because rapidly introducing cold air into the gland area can cause thermal shock and damage to the delicate carbon segments and sealing surfaces. Allowing the gland to cool gradually helps prevent this potential damage.
The other options are incorrect because they do not address the primary concern of avoiding thermal shock to the turbine gland components.
Related Questions
#583 An overheated bearing in the main propulsion unit is indicated by _______________.#584 The original bridge gage reading for a reduction gear bearing was measured as 0.008 inches. A year later, the bridge gage reading for the same bearing is 0.010 inches. This indicates _______________.#586 To prevent damage to the turning gear mechanism, which of the following procedures must be carried out before the turning gear is engaged? #587 To stop the rotor of a main turbine while underway at sea you should _______________.#588 The jacking gear must be engaged as quickly as possible when securing the main turbines in order to _______________.