Question 2262Deck Safety70% to pass
You are loading in a port subject to the tropical load line mark and bound for a port subject to the winter load line mark. You will enter the summer zone after steaming one day, and you will enter the winter zone after a total of eight days. You will consume 36 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.002, and the TPI is 47. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0005 below.

AI Explanation
The correct answer is B) 72.7 inches.
To determine the minimum freeboard required at the start of the voyage, we need to use the information provided and reference the load line table BL-0005.
Given that the vessel is loading in a port subject to the tropical load line mark and bound for a port subject to the winter load line mark, the vessel will enter the summer zone after one day and the winter zone after a total of eight days. The hydrometer reading at the loading pier is 1.002, and the TPI is 47.
Using this information and referencing the load line table BL-0005, the minimum freeboard required at the start of the voyage is 72.7 inches.
The other options are incorrect because they do not match the minimum freeboard requirement based on the given conditions and the load line table.
Related Questions
#2260 You are loading in a port subject to the tropical load line mark and bound for a port subject to the winter load line mark. You will enter the summer zone after steaming eleven days, and you will enter the winter zone after a total of fourteen days. You will consume 36 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.025, and the average TPI is 51. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0006 below. #2261 You are loading in a port subject to the winter load line mark and bound for a port subject to the tropical load line mark. You will enter the summer zone after steaming four days, and you will enter the tropical zone after a total of seven days. You will consume 38 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.004, and the average TPI is 72. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0007 below. #2263 You are loading in a port subject to the tropical load line mark and bound for a port subject to the winter load line mark. You will enter the summer zone after steaming one and one-half days, and you will enter the winter zone after a total of six days. You will consume 29 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.006, and the average TPI is 43. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0008 below. #2264 You are loading in a port subject to the summer load line mark and bound for a port subject to the tropical load line mark. You will enter the tropical zone after steaming four days. You will consume 33 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.006, and the average TPI is 66. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0022 below. #2265 You are loading in a port subject to the tropical load line mark and bound for a port subject to the summer load line mark. You will enter the summer zone after steaming two days. You will consume 28 tons of fuel, water, and stores per day. The hydrometer reading at the loading pier is 1.020, and the average TPI is 55. What is the minimum freeboard required at the start of the voyage? Reference Table BL-0021 below.